Exam Number:   642-902
Associated Certifications:   CCNP, CCIP and CCDP
Duration:   120 minutes (52 questions)
Available Languages:   English, Japanese

http://www.packet-lab.com/blog/difference-between-bsci-642-901-and-route-642-902-exam-blueprints/

certforumz

#1
642-902 Exam Objectives:

1.0 Implement an EIGRP based solution, given a network design and a set of requirements
2.0 Implement a multi-area OSPF Network, given a network design and a set of requirements
3.0 Implement an eBGP based solution, given a network design and a set of requirements
4.0 Implement an IPv6 based solution, given a network design and a set of requirements
5.0 Implement an IPv4 or IPv6 based redistribution solution, given a network design and a set of requirements
6.0 Implement Layer 3 Path Control Solution
7.0 Implement basic teleworker and branch services

642-901 Objectives (Old):

1. Describe and implement EIGRP operations
2. Describe and  implement multiarea OSPF oprations
3. Describe integrated IS-IS
4. Describe and implement Cisco IOS routing features
5. Implement BGP for enterprise ISP connectivity
6. Describe IP multicasting
7. Configure and verify multicast forwarding
8. Configure route filtering and redistribution
9. Describe and implement IPv6

Mapping of old and new exam objectives:
1 (EGRP)        ---- 1
2 (OSPF) ----2
3 (IS-IS) -- Removed in the new Route Exam
4 (Implement Cisco IOS routing features) --> 4, Describe and implement Cisco IOS routing features and  8. Configure route filtering and redistribution
5 (BGP for enterprise ISP connectivity) --> 5
6 (Multicast) --> Removed in the new Route Exam
7 (Implement IPv6) --> 9

There are a few new topics in IPv6 implementation, otherwise, there seems to be nothing new in 902 version compared to it's predecessor 901.

642-902 Exam Objectives:

Implement an EIGRP based solution, given a network design and a set of requirements

Determine network resources needed for implementing EIGRP on a network
Create an EIGRP implementation plan
Create an EIGRP verification plan
Configure EIGRP routing
Verify EIGRP solution was implemented properly using show and debug commands
Document results of EIGRP implementation and verification

Implement a multi-area OSPF Network, given a network design and a set of requirements

Determine network resources needed for implementing OSPF on a network
Create an OSPF implementation plan
Create an OSPF verification plan
Configure OSPF routing
Verify OSPF solution was implemented properly using show and debug commands
Document results of OSPF implementation and verification plan

Implement an eBGP based solution, given a network design and a set of requirements

Determine network resources needed for implementing eBGP on a network
Create an eBGP implementation plan
Create an eBGP verification plan
Configure eBGP routing
Verify eBGP solution was implemented properly using show and debug commands
Document results of eBGP implementation and verification plan

Implement an IPv6 based solution, given a network design and a set of requirements

Determine network resources needed for implementing IPv6 on a network

Create an IPv6 implementation plan
Create an IPv6 verification plan
Configure IPv6 routing
Configure IPv6 interoperation with IPv4
Verify IPv6 solution was implemented properly using show and debug commands
Document results of IPv6 implementation and verification plan

Implement an IPv4 or IPv6 based redistribution solution, given a network design and a set of requirements

Create a redistribution implementation plan based upon the results of the redistribution analysis
Create a redistribution verification plan
Configure a redistribution solution
Verify that a redistribution was implemented
Document results of a redistribution implementation and verification plan
Identify the differences between implementing an IPv4 and IPv6 redistribution solution

Implement Layer 3 Path Control Solution

Create a Layer 3 path control implementation plan based upon the results of the redistribution analysis
Create a Layer 3 path control verification plan
Configure Layer 3 path control
Verify that a Layer 3 path control was implemented
Document results of a Layer 3 path control implementation and verification plan

Implement basic teleworker and branch services


Describe broadband technologies
Configure basic broadband connections
Describe basic VPN technologies
Configure GRE
Describe branch access technologies